Bogandana Mini Hydro Power Project was commissioned in 2009 & it is fed by Weli oya located in Badulla. The capacity of this power plant is 5.0 Mw.
Capacity
5.0 MW
Design Flow
6.9 m3 / Sec
River Catchment
Weli oya
Effective Catchment Area
89kmĀ²
Head
92m
Channel Length
3928m
Penstock Length
258m
Commissioned
Oct 13, 2009
Turbine Type
Francis
Badulla
1.0 MW
Ratnapura
3.0 MW
Kandy
2.4 MW
4.0 MW
2.5 MW
1.5 MW
2.0 MW
4.2 MW
Kegalle
1.3 MW
10.5 MW